Bhotekoshi hydropower rebuild stalled as government decision waits
More than two months after the Bhotekoshi flood damaged 14 hydropower projects worth over Rs 12.46 billion, rebuilding has yet to begin as operators wait for a government decision on funding, insurance and design.
Published November 3, 2026 6:53 pm GMT+0545
Reconstruction of 14 hydropower projects damaged by the Bhotekoshi flood in Rasuwa and Nuwakot has stalled, more than two months after the disaster, as operators wait for the government to decide how rebuilding will be funded and designed.
Preliminary estimates put the damage at more than Rs 12.46 billion. Seven of the projects belong to the Nepal Electricity Authority and its subsidiaries and seven to private developers. Structures, access roads and bridges were damaged, and some sites still cannot be reached easily.
The Energy Ministry says it will settle the rebuilding approach only after the post-disaster needs assessment report is finalised. Ministry spokesperson Mohan Kumar Shakya said tentative damage data exists but the final picture cannot be stated until that report arrives, and discussions on the rebuilding model are still under way.
The share market, live
The NEPSE index, top movers and sectors, updated through the trading day.
Chilime Hydropower has called tenders to clear debris from its underground powerhouse, but other projects have not been able to move forward. Rasuwagadhi Hydropower is still collecting damage details and preparing insurance claims with surveyors, while studying whether rebuilding remains financially viable.
Company secretary Naranath Neupane said work cannot start until the government's technical report and rebuilding model arrive, including whether the old design can be restored or a new design is needed. He said the company has paid bank interest but cannot meet principal payments, and missed an Employees Provident Fund instalment.
Private producers say a government package is essential. Langtang Khola Hydropower manager and Independent Power Producers Association Nepal secretary Bijay Mohan Bhattarai said insurance money alone will not cover rebuilding, which could take two more years for projects already in operation, with lost income and interest adding to costs. He warned projects could close permanently if decisions are delayed.
Access is a further obstacle. About six bridges are needed to reach Rasuwagadhi's headworks, desander and powerhouse, two to be built by the company and four by the government. A Bailey bridge at Syafrubesi helps movement but cannot carry heavy construction equipment, and producers say a bridge able to carry 50 tonnes is needed alongside permanent bridges.
The Electricity Regulatory Commission is studying how costs should be shared between insurance, relief funds and concessional loans, and what effect any of it would have on consumer tariffs. A scientific committee is also studying the unusual flood itself. For operators, the central complaint remains time: every delay raises costs and debt.
How we report: Editorial Policy Corrections Report an error
Ask once. Get the answer.
Nepal's own search engine, with quick answers right at the top.









